News & Events

2018-04-04 08:51:05pm

Arab Brothers Company Hands Over Jaba Nuba Transmission Phase II, funded by USAID


Arab Brothers acknowledges its achievement in completing AID-294-TO-16-00005 Jaba Nuba Transmission Phase II; on time, and that too in an efficient way. All works on this Contract including 2 pumping stations, 18km of Steel pipes, and refurbishing of existing 12km of DN500mm ductile Iron pipes have been satisfactorily completed for $7.8 M. Representatives of USAID West Bank/Gaza, Palestine Water Authority; AECOM, and Arab Brothers Company have attended this event.